At the November 13th City Council
meeting, a resident asked me several questions about the boat launch
project--specifically about the bidding process, and how we plan to
finance the city’s matching share of the grant-funded process.
Unfortunately, I was not prepared to answer those questions accurately
because I did not have the exact figures at hand. Rather than give the
questioner inaccurate figures, I said I would answer the questions
later, or at the next meeting.
I’m posting the answers to those questions on the city’s
web site now, as a way to inform the gentleman who brought them up as
well as to provide some information on how and when these decisions were
made for any resident of the city who might not have kept up with the
process.
I commend our Council President, Ed
Podmanik, for being very flexible during the Citizens’ Commentary
portion of our meetings, by allowing residents to voice their opinions
on issues but without allowing abuse of that privilege.
The next scheduled council meeting was Nov. 27th, but it was
postponed until December 4th, due to the fact that our late, great Ward
1 Councilwoman Joyce Hanks had passed away earlier in the day. I was
prepared to answer all of the questions Dec. 4th, but the resident who
asked them chose not to attend. So I’d like to spell out all the details
here on our web site for that resident, or any interested resident, to
get the information:
Q: “How do you go from sealed bids opened on FRIDAY, to a decision made
on MONDAY to ODNR’s approval, and passed at a special meeting on
TUESDAY?
A:
Bids were first advertised Aug. 17, but all were rejected as too high.
Bids were advertised a second time, after reformulating requirements, on
Sept. 27. Sealed bids were opened publicly Oct. 12th at City Hall, with
the bidders, the city engineer (K-S Engineering), the mayor and service
director all present. Bids included: $1,668,834 (Huffman Construction);
$1,441,755 (Martin Enterprises) $1,435,277 (North Coast Construction).
The lowest bid, $1,417,972 by Mark Haynes Construction was vetted and
declared best by both our service director and city engineer.
I asked council to schedule a brief special meeting before our regularly
scheduled finance committee and work session meetings on October 16, in
order to approve the lowest and best bid and start the in-water phase of
construction before the weather becomes inclement. We are under a
completion deadline to finish the project under terms of the state grant
and we hope to get the in-water part of the project--the ramp and
seawall--done before the lake freezes. We’ll do the on-shore work, the
parking lots, etc. in the spring, and, weather permitting, in plenty of
time to meet our completion deadline.
Q: What about cost? (A number of questions were asked and statements
made on Oct. 13th that indicated that my past statements about how much
the city’s share of the construction cost would be, and about how it
will be paid.)
A.
The fact is that the amount of the city’s share of the cost changed
several times over the past four years, due mainly to increased
construction costs (inflation) and changes to the plan that were
required either by ODNR, the Corps of Engineers, Coastal Management and
Ohio EPA. Adjusting to all the changes in requirements and plans took
time and the process was further extended by delays in receiving the
required permits from all of the state and federal agencies involved.
All of that contributed to increases in the city’s matching share of the
project. Also, back when the Park Board first applied for the grant
(which was rejected three times before it was approved) we believed we
could offset some of the matching funds with “in-kind” work performed by
our Service Department. In the end, “in-kind” matches were not allowed.
The final amount of the city’s share (and contingencies will probably
add to this before we’re done) is a $552,972 share of the $1,417,972
total cost of constructing the boat launch ramp. We do not have that
much money in the 265 Parks New Construction account, so Council
approved a $500,000 note backed by our 401 Capital Improvement Fund to
make up the difference. Even if there is zero new construction to
bolster the 265 account, a worst-case scenario, is that the 401 account,
funded at the rate of about $150,000 annually by inside tax mills, can
repay the note in three and a half years.
Q: “Why don’t the plans show any source of electricity?”
A:
The only lighting involved in the in-water part of the project in this
phase is the navigational aid lamps on the seawall that mark the
entrance to the ramp. These navigational lights will be solar-powered,
so no source of electricity will be needed.
Q: “Why is there no gate house in the plans?”
A:
No gate house is needed because there will be no launch fees to collect.
Our intention all along, from the very first discussions at Park Board
meetings in 2001, has been to provide a free launch ramp for our
residents and to attract more non-residents to the area. We’ll be
holding another community forum at 7 p.m. Dec. 20th, at City Hall, to
ask residents for their suggestions as to what they’d like to see
replace the empty storefronts in Shoreway Shopping Center. Those
suggestions will inform our urban renewal planner for that area. The
plan is being put together with a grant acquired through NOACA’s
Transportation for Livable Communities Initiative.
This project was not done in a hurry. The Park Board began working
toward the grant process well over six years ago. Sheffield Lake’s
Planning Commission worked long and hard to formulate our Master Plan;
they held well-attended community consensus meetings and conducted
citizen surveys which garnered over 1,800 responses. More residents
responded to those surveys than voted in our last election. More
Sheffield Lake residents responded to our Master Plan surveys than
Lorain County residents responded to the County’s Master Plan Survey.
Clearly, this community wants this boat launch ramp.
Surveys and meetings informed all decisions, and the boat launch project
was dealt with by City Council and nearly every other city board and
committee all through the long process of applying for grants and
planning these improvements to Community Park. My own personal thoughts
aside, our city’s Master Plan calls for a boat launch ramp. So a boat
launch ramp is what we’re building. When this phase of the process is
done we’ll continue to apply for grants to help us add a boardwalk and
other amenities to Community Park in the future.